Suburban HOA Sewer and Asphalt Replacement

Willowbrook, IL
Asphalt/Sewer Repairs

Remove and replace roughly 56,000 square feet of pavement

Utilize camera to scope all sanitation lines to determine condition of pipes

Saved the Association $500k+ by working with engineers to refine the proper scope of the project

Negotiated $60k credit from sub-contractors during pre-construction phase

Credited Association $42k at end of project for coming in under-budget through value engineering assessments during construction